- Site Mobilization- September 5, 2007
- First Concrete Placement- February 29, 2008
- Start Steel Erection- August 21, 2008
- Start Installation of Boiler Pressure Parts- April 17, 2009
- Start Erection of Turbine Generator- August 3, 2009
- First Fire and Steam Turbine Roll- April 1, 2011
- Unit 1 Completion- Between August 1, 2011 and December 1, 2011
- Unit 2 Completion- Between March 1, 2012 and August 1, 2012
|
|
|
| |
|
|
| |
|